Sainsbury’s, Thanet
ISG PLC, May-14 to Jan-16Client: Sainsbury’s
Main Contractor: ISG PLC
Start Date: May 2014
Completion Date: January 2016
Division: Surfacing
Overview
O’Rourke Contracting worked alongside ISG on the £19m redevelopment of Sainsbury’s, Thanet. The works included the reconstruction/ extension of the existing car park as well as an underground car park.
This project had an accelerated programme to meet clients date requirements which we supported through flexible working hours and night work. Working on the underground car park posed issues in terms of height restrictions and meant that alternative plant and machinery had to be used. It was also important to keep disruption to traffic and residents of the surrounding areas to a minimum.
Scope of Works
- Reinstatement of drainage and service trenches
- Supply and lay base, binder and surface course to car parks
- Working to height restrictions
- 278 Works
- Binder and Surface course to Footways
- Reconfigure site access