HS2 – Old Oak Common
Vinci, Sep-16 to Dec-18Client: Bombardier
Main Contractor: Vinci/ Taylor Woodrow
Start Date: September 2016
Completion Date: December 2018
Division: Surfacing
Overview
O’Rourke Contracting PLC were awarded the contract for construction of new access roads and lorry park to the £142m HS2 station Old Oak Common. This project is one of the largest regeneration projects in London since the Olympics and comprised of over 16,000m2 of surfacing works.
We worked closely with Vinci throughout this contract to offer suitable alternatives and suggest appropriate materials for the works and have maintained a flexible approach to ensure that timescales are met and to minimise disruption to the surrounding area.
Scope of Works
- Plane off existing carriageway material
- Relay base, binder and surface course
- Reconfigure existing site access
- Testing of materials