HS2 – Old Oak Common

HS2 – Old Oak Common

Vinci, Sep-16 to Dec-18

Client: Bombardier

Main Contractor: Vinci/ Taylor Woodrow

Start Date: September 2016

Completion Date: December 2018

Division: Surfacing

Overview
O’Rourke Contracting PLC were awarded the contract for construction of new access roads and lorry park to the £142m HS2 station Old Oak Common. This project is one of the largest regeneration projects in London since the Olympics and comprised of over 16,000m2 of surfacing works.

We worked closely with Vinci throughout this contract to offer suitable alternatives and suggest appropriate materials for the works and have maintained a flexible approach to ensure that timescales are met and to minimise disruption to the surrounding area.

Scope of Works

  • Plane off existing carriageway material
  • Relay base, binder and surface course
  • Reconfigure existing site access
  • Testing of materials

"Our clients include some of the biggest names in the construction world. We are proud that we surpass their expectations."

van photo